Project
MilestoneS
| Task |
Due Date |
Status |
| Brainstorm Ideas # 1 |
1/27/03 |
Complete |
| Visit EST in New York |
1/30/03 |
Complete |
| Investigate potential interactions |
2/5/03 |
Complete |
| Full Spectrum Experience Outline |
2/23/03 |
Complete |
| Demo VM # 1 |
2/28/03 |
Complete |
| Design Logo |
2/28/03 |
Complete |
| |
|
|
| Cycle 3 Presentations |
2/28/03 |
|
| GET SCRIPT |
3/3/03 |
Not Complete |
| Design Full Spectrum Postcard |
3/4/03 |
Not Complete |
| Design Full Spectrum WebSite |
3/5/03 |
Not Complete |
| Workshop Script |
3/6 - 3/7 |
Not Complete |
| Finalize Experience Design |
3/6/03 |
Not Complete |
| Setup Full Spectrum in New York |
3/23/03 |
Not Complete |
| Run Full Spectrum |
3/27 – 3/29 |
Not Complete |
| Soft Opening |
4/22/03 |
Not Complete |
| Document Full Spectrum |
|
Evolving |
|
|
| |
|