ITI-Fall2002





Project Start:
Project Finish:
Tue 10/1/02
Wed 12/11/02


Tasks


ID
Task Name
DurationStartFinishResource Names% Complete
1
Virtual Meditation #1
38 days?Wed 10/2/02Wed 11/20/02 0%
2
Second Avenue Setup
4 days?Fri 10/18/02Tue 10/22/02 0%
3
Receive delivery of lightboard cables
1 day?Fri 10/18/02Fri 10/18/02Cheryl0%
4
Move lights to lightboard
1 day?Sun 10/20/02Sun 10/20/02Cheryl0%
5
Buy Black Sheets to hide projector bleed
1 day?Mon 10/21/02Mon 10/21/02 0%
6
Dress room w/sheets
1 day?Tue 10/22/02Tue 10/22/02 0%
7
CSCW Conference
38 daysWed 10/2/02Wed 11/20/02 0%
8
Obtain Room Assignment & Dimensions
0 daysWed 10/2/02Wed 10/2/02Ryan0%
9
Obtain Pictures/Video of Room
0 daysMon 10/14/02Mon 10/14/02Ryan0%
10
Create Set Schematic for New Orleans
2 daysMon 10/14/02Tue 10/15/02Cheryl0%
11
Provide Conference with Video Footage
0 daysTue 10/15/02Tue 10/15/02Cheryl0%
12
Determine Travel Solutions
1 wkThu 10/17/02Tue 10/22/02Ryan,Brenda0%
13
CSCW Travel & Setup
2 daysMon 11/18/02Tue 11/19/02All0%
14
CSCW Performance
1 dayMon 11/18/02Mon 11/18/02All0%
15
CSCW Strike & Return
2 daysTue 11/19/02Wed 11/20/02All0%
16
Portability
13 daysMon 10/14/02Wed 10/30/02 0%
17
Receive new Laptops
0 wksTue 10/15/02Tue 10/15/02Cheryl0%
18
Migrate to Laptops
2 wksWed 10/16/02Mon 10/28/02Cheryl0%
19
Receive Portable Screen
0 daysMon 10/14/02Mon 10/14/02Hunter0%
20
Purchase Travel Kits for Lighting Trees
0 daysWed 10/30/02Wed 10/30/02 0%
21
Regionalization
10 daysWed 10/16/02Mon 10/28/02 0%
22
Obtain Contact Information of Italian Translators
0 daysWed 10/23/02Wed 10/23/02 0%
23
Research Translations for other languages
2 wksWed 10/16/02Mon 10/28/02 0%
24      
25
Uberproject
54 days?Wed 10/2/02Wed 12/11/02 0%
26
Scriptwriting
21 daysTue 10/15/02Mon 11/11/02 0%
27
First draft finished
0 daysTue 10/15/02Tue 10/15/02Hunter0%
28
First Read-Through
0 daysSun 10/20/02Sun 10/20/02Hunter0%
29
Second Draft Finished
0 daysWed 10/30/02Wed 10/30/02Hunter0%
30
Final Draft Finished
0 daysMon 11/11/02Mon 11/11/02Hunter0%
31
Acting/Directing
43 daysWed 10/16/02Tue 12/10/02 0%
32
Casting Process
5 daysWed 10/16/02Mon 10/21/02Ryan0%
33
First Read-Through
0 daysSun 10/20/02Sun 10/20/02All0%
34
Rehearsals Begin
0 daysWed 11/6/02Wed 11/6/02Cast0%
35
Rehearsal Process
25 daysFri 11/8/02Tue 12/10/02Cast0%
36
Vocal Recordings (Inner Monologues)
2 daysFri 11/8/02Sun 11/10/02Cast,Ryan0%
37
Technical Design
42 days?Wed 10/2/02Wed 11/27/02 0%
38
Technology Exploration Documentation
3 daysWed 10/2/02Fri 10/4/02Cheryl0%
39
End-to-End Testing
1 dayTue 11/19/02Tue 11/19/02All0%
40
Infrared Focus Switching
39 days?Mon 10/7/02Wed 11/27/02 0%
41
Investigate IR Technologies
12 daysMon 10/7/02Mon 10/21/02Cheryl,Lakshmi0%
42
Purchase IR Parts
0 daysMon 10/21/02Mon 10/21/02Cheryl,Lakshmi0%
43
Receive IR Parts
0 daysMon 10/28/02Mon 10/28/02Cheryl,Lakshmi0%
44
Construct IR Prototypes
16 daysMon 10/28/02Fri 11/15/02Lakshmi0%
45
System Revisions & Robustness
5 days?Wed 11/20/02Tue 11/26/02Lakshmi0%
46
Final IR Delivery
0 daysWed 11/27/02Wed 11/27/02Lakshmi0%
47
Computing Infrastructure
39 days?Mon 10/7/02Wed 11/27/02 0%
48
Investigate Audio Streaming
12 daysMon 10/7/02Mon 10/21/02Cheryl,Lakshmi0%
49
Establish Prototype Network
12 daysTue 10/22/02Wed 11/6/02Cheryl,Lakshmi0%
50
Develop Client Software
9 days?Thu 11/7/02Mon 11/18/02Cheryl0%
51
Systems Revisions & Robustness
5 daysWed 11/20/02Tue 11/26/02Cheryl0%
52
Final Network Delivery
0 daysWed 11/27/02Wed 11/27/02Cheryl0%
53
Production
13 daysWed 10/16/02Fri 11/1/02 0%
54
Set Designs Finished
0 daysFri 11/1/02Fri 11/1/02Cheryl0%
55
Costume Designs Finished
0 daysFri 11/1/02Fri 11/1/02Cheryl0%
56
Investigate Performance Space
7 daysWed 10/16/02Wed 10/23/02Ryan0%
57
Performances
9 daysSun 12/1/02Wed 12/11/02 0%
58
Load-In
1 daySun 12/1/02Sun 12/1/02All0%
59
Tech Rehearsals
1 dayTue 12/3/02Tue 12/3/02All,Cast0%
60
Dress Rehearsals
1 dayWed 12/4/02Wed 12/4/02All,Cast0%
61
End of Cycle 2
2 daysThu 12/5/02Fri 12/6/02All,Cast0%
62
External Exhibitions
1 dayWed 12/11/02Wed 12/11/02All,Cast0%

Resources


IDNameGroupMax UnitsPeak Units
1Ryan 100%300%
2All + Cast 100%0%
3Cast 100%200%
4Hunter 100%0%
5Cheryl 100%400%
6All 100%300%
7Brenda 100%100%
8Lakshmi 100%200%
9  100%0%
1044 100%0%

Assignments


Task IDTask NameResource NameWorkStartFinish% Work Complete
3Receive delivery of lightboard cablesCheryl8 hrsFri 10/18/02Fri 10/18/020%
4Move lights to lightboardCheryl8 hrsSun 10/20/02Sun 10/20/020%
8Obtain Room Assignment & DimensionsRyan0 hrsWed 10/2/02Wed 10/2/020%
9Obtain Pictures/Video of RoomRyan0 hrsMon 10/14/02Mon 10/14/020%
10Create Set Schematic for New OrleansCheryl16 hrsMon 10/14/02Tue 10/15/020%
11Provide Conference with Video FootageCheryl0 hrsTue 10/15/02Tue 10/15/020%
12Determine Travel SolutionsRyan40 hrsThu 10/17/02Tue 10/22/020%
12Determine Travel SolutionsBrenda40 hrsThu 10/17/02Tue 10/22/020%
13CSCW Travel & SetupAll16 hrsMon 11/18/02Tue 11/19/020%
14CSCW PerformanceAll8 hrsMon 11/18/02Mon 11/18/020%
15CSCW Strike & ReturnAll16 hrsTue 11/19/02Wed 11/20/020%
17Receive new LaptopsCheryl0 hrsTue 10/15/02Tue 10/15/020%
18Migrate to LaptopsCheryl80 hrsWed 10/16/02Mon 10/28/020%
19Receive Portable ScreenHunter0 hrsMon 10/14/02Mon 10/14/020%
27First draft finishedHunter0 hrsTue 10/15/02Tue 10/15/020%
28First Read-ThroughHunter0 hrsSun 10/20/02Sun 10/20/020%
29Second Draft FinishedHunter0 hrsWed 10/30/02Wed 10/30/020%
30Final Draft FinishedHunter0 hrsMon 11/11/02Mon 11/11/020%
32Casting ProcessRyan40 hrsWed 10/16/02Mon 10/21/020%
33First Read-ThroughAll0 hrsSun 10/20/02Sun 10/20/020%
34Rehearsals BeginCast0 hrsWed 11/6/02Wed 11/6/020%
35Rehearsal ProcessCast200 hrsFri 11/8/02Tue 12/10/020%
36Vocal Recordings (Inner Monologues)Cast16 hrsFri 11/8/02Sun 11/10/020%
36Vocal Recordings (Inner Monologues)Ryan16 hrsFri 11/8/02Sun 11/10/020%
38Technology Exploration DocumentationCheryl24 hrsWed 10/2/02Fri 10/4/020%
39End-to-End TestingAll8 hrsTue 11/19/02Tue 11/19/020%
41Investigate IR TechnologiesCheryl96 hrsMon 10/7/02Mon 10/21/020%
41Investigate IR TechnologiesLakshmi96 hrsMon 10/7/02Mon 10/21/020%
42Purchase IR Parts Cheryl0 hrsMon 10/21/02Mon 10/21/020%
42Purchase IR Parts Lakshmi0 hrsMon 10/21/02Mon 10/21/020%
43Receive IR PartsCheryl0 hrsMon 10/28/02Mon 10/28/020%
43Receive IR PartsLakshmi0 hrsMon 10/28/02Mon 10/28/020%
44Construct IR PrototypesLakshmi128 hrsMon 10/28/02Fri 11/15/020%
45System Revisions & RobustnessLakshmi40 hrsWed 11/20/02Tue 11/26/020%
46Final IR DeliveryLakshmi0 hrsWed 11/27/02Wed 11/27/020%
48Investigate Audio StreamingCheryl96 hrsMon 10/7/02Mon 10/21/020%
48Investigate Audio StreamingLakshmi96 hrsMon 10/7/02Mon 10/21/020%
49Establish Prototype NetworkCheryl96 hrsTue 10/22/02Wed 11/6/020%
49Establish Prototype NetworkLakshmi96 hrsTue 10/22/02Wed 11/6/020%
50Develop Client SoftwareCheryl72 hrsThu 11/7/02Mon 11/18/020%
51Systems Revisions & RobustnessCheryl40 hrsWed 11/20/02Tue 11/26/020%
52Final Network DeliveryCheryl0 hrsWed 11/27/02Wed 11/27/020%
54Set Designs FinishedCheryl0 hrsFri 11/1/02Fri 11/1/020%
55Costume Designs FinishedCheryl0 hrsFri 11/1/02Fri 11/1/020%
56Investigate Performance SpaceRyan56 hrsWed 10/16/02Wed 10/23/020%
58Load-InAll8 hrsSun 12/1/02Sun 12/1/020%
59Tech RehearsalsAll8 hrsTue 12/3/02Tue 12/3/020%
59Tech RehearsalsCast8 hrsTue 12/3/02Tue 12/3/020%
60Dress RehearsalsAll8 hrsWed 12/4/02Wed 12/4/020%
60Dress RehearsalsCast8 hrsWed 12/4/02Wed 12/4/020%
61End of Cycle 2All16 hrsThu 12/5/02Fri 12/6/020%
61End of Cycle 2Cast16 hrsThu 12/5/02Fri 12/6/020%
62External ExhibitionsAll8 hrsWed 12/11/02Wed 12/11/020%
62External ExhibitionsCast8 hrsWed 12/11/02Wed 12/11/020%


Microsoft Home Page
Microsoft Project Home Page