| Task ID | Task Name | Resource Name | Work | Start | Finish | % Work Complete |
| 3 | Receive delivery of lightboard cables | Cheryl | 8 hrs | Fri 10/18/02 | Fri 10/18/02 | 0% |
| 4 | Move lights to lightboard | Cheryl | 8 hrs | Sun 10/20/02 | Sun 10/20/02 | 0% |
| 8 | Obtain Room Assignment & Dimensions | Ryan | 0 hrs | Wed 10/2/02 | Wed 10/2/02 | 0% |
| 9 | Obtain Pictures/Video of Room | Ryan | 0 hrs | Mon 10/14/02 | Mon 10/14/02 | 0% |
| 10 | Create Set Schematic for New Orleans | Cheryl | 16 hrs | Mon 10/14/02 | Tue 10/15/02 | 0% |
| 11 | Provide Conference with Video Footage | Cheryl | 0 hrs | Tue 10/15/02 | Tue 10/15/02 | 0% |
| 12 | Determine Travel Solutions | Ryan | 40 hrs | Thu 10/17/02 | Tue 10/22/02 | 0% |
| 12 | Determine Travel Solutions | Brenda | 40 hrs | Thu 10/17/02 | Tue 10/22/02 | 0% |
| 13 | CSCW Travel & Setup | All | 16 hrs | Mon 11/18/02 | Tue 11/19/02 | 0% |
| 14 | CSCW Performance | All | 8 hrs | Mon 11/18/02 | Mon 11/18/02 | 0% |
| 15 | CSCW Strike & Return | All | 16 hrs | Tue 11/19/02 | Wed 11/20/02 | 0% |
| 17 | Receive new Laptops | Cheryl | 0 hrs | Tue 10/15/02 | Tue 10/15/02 | 0% |
| 18 | Migrate to Laptops | Cheryl | 80 hrs | Wed 10/16/02 | Mon 10/28/02 | 0% |
| 19 | Receive Portable Screen | Hunter | 0 hrs | Mon 10/14/02 | Mon 10/14/02 | 0% |
| 27 | First draft finished | Hunter | 0 hrs | Tue 10/15/02 | Tue 10/15/02 | 0% |
| 28 | First Read-Through | Hunter | 0 hrs | Sun 10/20/02 | Sun 10/20/02 | 0% |
| 29 | Second Draft Finished | Hunter | 0 hrs | Wed 10/30/02 | Wed 10/30/02 | 0% |
| 30 | Final Draft Finished | Hunter | 0 hrs | Mon 11/11/02 | Mon 11/11/02 | 0% |
| 32 | Casting Process | Ryan | 40 hrs | Wed 10/16/02 | Mon 10/21/02 | 0% |
| 33 | First Read-Through | All | 0 hrs | Sun 10/20/02 | Sun 10/20/02 | 0% |
| 34 | Rehearsals Begin | Cast | 0 hrs | Wed 11/6/02 | Wed 11/6/02 | 0% |
| 35 | Rehearsal Process | Cast | 200 hrs | Fri 11/8/02 | Tue 12/10/02 | 0% |
| 36 | Vocal Recordings (Inner Monologues) | Cast | 16 hrs | Fri 11/8/02 | Sun 11/10/02 | 0% |
| 36 | Vocal Recordings (Inner Monologues) | Ryan | 16 hrs | Fri 11/8/02 | Sun 11/10/02 | 0% |
| 38 | Technology Exploration Documentation | Cheryl | 24 hrs | Wed 10/2/02 | Fri 10/4/02 | 0% |
| 39 | End-to-End Testing | All | 8 hrs | Tue 11/19/02 | Tue 11/19/02 | 0% |
| 41 | Investigate IR Technologies | Cheryl | 96 hrs | Mon 10/7/02 | Mon 10/21/02 | 0% |
| 41 | Investigate IR Technologies | Lakshmi | 96 hrs | Mon 10/7/02 | Mon 10/21/02 | 0% |
| 42 | Purchase IR Parts | Cheryl | 0 hrs | Mon 10/21/02 | Mon 10/21/02 | 0% |
| 42 | Purchase IR Parts | Lakshmi | 0 hrs | Mon 10/21/02 | Mon 10/21/02 | 0% |
| 43 | Receive IR Parts | Cheryl | 0 hrs | Mon 10/28/02 | Mon 10/28/02 | 0% |
| 43 | Receive IR Parts | Lakshmi | 0 hrs | Mon 10/28/02 | Mon 10/28/02 | 0% |
| 44 | Construct IR Prototypes | Lakshmi | 128 hrs | Mon 10/28/02 | Fri 11/15/02 | 0% |
| 45 | System Revisions & Robustness | Lakshmi | 40 hrs | Wed 11/20/02 | Tue 11/26/02 | 0% |
| 46 | Final IR Delivery | Lakshmi | 0 hrs | Wed 11/27/02 | Wed 11/27/02 | 0% |
| 48 | Investigate Audio Streaming | Cheryl | 96 hrs | Mon 10/7/02 | Mon 10/21/02 | 0% |
| 48 | Investigate Audio Streaming | Lakshmi | 96 hrs | Mon 10/7/02 | Mon 10/21/02 | 0% |
| 49 | Establish Prototype Network | Cheryl | 96 hrs | Tue 10/22/02 | Wed 11/6/02 | 0% |
| 49 | Establish Prototype Network | Lakshmi | 96 hrs | Tue 10/22/02 | Wed 11/6/02 | 0% |
| 50 | Develop Client Software | Cheryl | 72 hrs | Thu 11/7/02 | Mon 11/18/02 | 0% |
| 51 | Systems Revisions & Robustness | Cheryl | 40 hrs | Wed 11/20/02 | Tue 11/26/02 | 0% |
| 52 | Final Network Delivery | Cheryl | 0 hrs | Wed 11/27/02 | Wed 11/27/02 | 0% |
| 54 | Set Designs Finished | Cheryl | 0 hrs | Fri 11/1/02 | Fri 11/1/02 | 0% |
| 55 | Costume Designs Finished | Cheryl | 0 hrs | Fri 11/1/02 | Fri 11/1/02 | 0% |
| 56 | Investigate Performance Space | Ryan | 56 hrs | Wed 10/16/02 | Wed 10/23/02 | 0% |
| 58 | Load-In | All | 8 hrs | Sun 12/1/02 | Sun 12/1/02 | 0% |
| 59 | Tech Rehearsals | All | 8 hrs | Tue 12/3/02 | Tue 12/3/02 | 0% |
| 59 | Tech Rehearsals | Cast | 8 hrs | Tue 12/3/02 | Tue 12/3/02 | 0% |
| 60 | Dress Rehearsals | All | 8 hrs | Wed 12/4/02 | Wed 12/4/02 | 0% |
| 60 | Dress Rehearsals | Cast | 8 hrs | Wed 12/4/02 | Wed 12/4/02 | 0% |
| 61 | End of Cycle 2 | All | 16 hrs | Thu 12/5/02 | Fri 12/6/02 | 0% |
| 61 | End of Cycle 2 | Cast | 16 hrs | Thu 12/5/02 | Fri 12/6/02 | 0% |
| 62 | External Exhibitions | All | 8 hrs | Wed 12/11/02 | Wed 12/11/02 | 0% |
| 62 | External Exhibitions | Cast | 8 hrs | Wed 12/11/02 | Wed 12/11/02 | 0% |